NEW RAIL SIDING
GRAINCORP | CALLEEN
GRAINCORP CALLEEN – NEW RAIL SIDING
Taylor Rail Australia completed the construction of a new rail siding for GrainCorp at the Calleen site.
The siding is located on the Lake Cargelligo Branch of the Country Regional Network. The existing track is 104lbs rail on timber sleepers and classified as Class 3. The new rail siding is Track Class 1.
The works for the new Rail siding included:
The new track and associated civil works was constructed in two parts: Stage 1 within the GrainCorp owned private property and Stage 2 the works within the CRN managed Main Line corridor